Department of Energy Completes Key Milestone in Cleaning Up Idaho Facility
Last of 3,100 Cubic Meters of Transuranic Waste Leaves State Two Months Ahead of Schedule, Arrives at WIPP Disposal Facility
WASHINGTON, DC — The final shipment of transuranic waste to meet a 3,100 cubic meters project milestone, agreed to by the Department of (DOE) and the state of Id
was completed today. This re
The goal was to compl
INEEL Cumulative Cubic Meters of TRU Waste Disposed at WIPP
| Previous slide | Next slide | Back to first slide | View graphic version |